Tiskové zprávy

Project International Clinical Research Center Brno two years behind the schedule

From November 2008 to March 2009, auditors from the Supreme Audit Office (SAO) performed an audit of the state budget finances allotted for the realization of the project of constructing the International Clinical Research Centre in the premises of the St. Anne’s University Hospital in Brno. The Project ICRC Brno has been implemented since 2005. Over CZK 1.3 milliard were transferred into the state budget chapter 335 – Ministry of Health…

Risks of the R52 and R55 motorways’ procurements analyzed

From August 2008 to March 2009, auditors from the Supreme Audit Office (SAO) focused on the effectiveness of investments in the planned construction of a direct connection of Brno and Vienna via the R52 motorway. Among the audited bodies were the Ministry of Regional Development, the Ministry of Environment, the Road and Motorway Directorate of the Czech Republic, and the State Fund of Transport Infrastructure. Risk assessment analyses of the…